Grid infrastructure › Connection queue › Onshore wind

ONSHORE WIND · SPT

Harestanes West Wind Farm

Harestanes West Wind Farm is a 81 MW onshore wind project in planning, connecting to the SP Transmission (south Scotland) network at Harestanes West Wind Farm 132/33kV, with capacity due from July 2035. The connection agreement is held by Scottish Power Renewables (UK) Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Jul 2035 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-001075-2
Customer
Scottish Power Renewables (UK) Limited
Technology
Wind Onshore
Total capacity
81 MW
Change in this agreement
+25 MW
Capacity effective from
1 July 2035
Connection site
Harestanes West Wind Farm 132/33kV
Transmission owner
SP Transmission (south Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Scoping

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Harestanes West Wind Farm · Grid map

Other projects at Harestanes West Wind Farm 132/33kV

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem