Grid infrastructure β€Ί Connection queue β€Ί Solar + storage

SOLAR + STORAGE Β· NGET

Bramford (Tertiary)

Bramford (Tertiary) is a 57 MW solar + storage project built and connected, connecting to the National Grid (England & Wales) network at Bramford 400kV Substation. The connection agreement is held by Damsongreen Energyfarm Limited.

Project stageOperating
  1. Planning (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-001016
Customer
Damsongreen Energyfarm Limited
Technology
Energy Storage System, PV Array (Photo Voltaic/solar)
Total capacity
57 MW
Already connected
57 MW
Connection site
Bramford 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Built

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Bramford Β· Grid map

Other projects at Bramford 400kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem