Solar project 632, Beaver County

Solar project 632, Beaver County is a 3.0 MW solar request built and operating in the West interconnection queue, in Beaver County, Utah, connecting to PacifiCorp.

Queue statusOperating
  1. PlanningQueued Nov 2014 (completed)
  2. ConsentedNov 2015 (completed)
  3. Construction (completed)
  4. OperatingTarget May 2017 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
632
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Thermo No. 1 BE-01, LLC
Connection point (POI)
Circuit SML21 out of South Milford substation
Location
Beaver County, Utah
Technology
Solar: 3.0 MW
Total requested
3.0 MW
Service type
Network resource (NRIS)
Study phase
IA signed 11/30/15
Queue status
Operational
Entered queue
12 November 2014
Agreement signed
30 November 2015
Proposed online date
May 2017

Location

Marker shows the centre of Beaver County; the queue data does not give exact sites.