Mystic Ridge

Mystic Ridge is a 412 MW solar + storage request withdrawn in the CAISO interconnection queue, in San Benito County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2023 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
2255
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
LOS BANOS 500 kV
Location
San Benito County, California
Technology
Solar: 206 MW · Battery: 206 MW
Total requested
412 MW
Service type
Network resource (NRIS)
Study phase
Caiso Cluster 15 Unvalidated
Queue status
Withdrawn
Entered queue
17 April 2023
Proposed online date
April 2028
Withdrawn
December 2025

Location

Marker shows the centre of San Benito County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Benito County