SOLAR · CAISO

Westlands Solar Farms PV2

Westlands Solar Farms PV2 is a 1.5 MW solar request withdrawn in the CAISO interconnection queue, in Fresno County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2014 (completed)
  2. Withdrawn / abandonedApr 2015 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1091
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Gates-Coalinga 70 kV Line #1
Location
Fresno County, California
Technology
Solar: 1.5 MW
Total requested
1.5 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
14 May 2014
Proposed online date
August 2015
Withdrawn
April 2015

Location

Marker shows the centre of Fresno County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Fresno County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem