United States › Grid › Interconnection queues › Pennsylvania

COAL · PJM

Greene Energy Resource Recovery Project

Greene Energy Resource Recovery Project is a 525 MW coal request withdrawn in the PJM interconnection queue, in Greene County, Pennsylvania, connecting to APS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2001 (completed)
  2. Withdrawn / abandonedMar 2013 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G51_W60
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
Hatfield Ferry 500 kV
Location
Greene County, Pennsylvania
Technology
Coal: 525 MW
Total requested
525 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Withdrawn
Entered queue
31 July 2001
Proposed online date
August 2015
Withdrawn
March 2013

Location

Marker shows the centre of Greene County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Greene County