United States › Grid › Interconnection queues › Florida

SOLAR · SOUTHEAST

Solar project 253, Hardee County

Solar project 253, Hardee County is a 74.9 MW solar request built and operating in the Southeast interconnection queue, in Hardee County, Florida, connecting to Duke Energy Florida.

Queue statusOperating
  1. PlanningQueued May 2019 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingAug 2022 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
253
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Florida
Developer
Duke Energy Florida, LLC
Connection point (POI)
Singletary Substation
Location
Hardee County, Florida
Technology
Solar: 74.9 MW
Total requested
74.9 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
1 May 2019
Proposed online date
August 2022
Came online
August 2022

Location

Marker shows the centre of Hardee County; the queue data does not give exact sites.

Power plants in Florida · Transmission lines in Florida

Other requests in Hardee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem