United States β€Ί Grid β€Ί Interconnection queues β€Ί Florida

GAS Β· SOUTHEAST

Gas project 76, Hardee County

Gas project 76, Hardee County is a 566 MW gas request withdrawn in the Southeast interconnection queue, in Hardee County, Florida, connecting to Duke Energy Florida.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2007 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
76
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Florida
Developer
Masked
Location
Hardee County, Florida
Technology
Gas: 566 MW
Total requested
566 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
21 December 2007
Proposed online date
December 2011

Location

Marker shows the centre of Hardee County; the queue data does not give exact sites.

Power plants in Florida Β· Transmission lines in Florida

Other requests in Hardee County