Onshore wind project 79, Sweet Grass County

Onshore wind project 79, Sweet Grass County is a 200 MW onshore wind request withdrawn in the West interconnection queue, in Sweet Grass County, Montana, connecting to NorthWestern Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2008 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
79
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
230kV Bus at Broadview 500kV:230kV Station
Location
Sweet Grass County, Montana
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
17 January 2008
Proposed online date
December 2013

Location

Marker shows the centre of Sweet Grass County; the queue data does not give exact sites.

Power plants in Montana Β· Transmission lines in Montana

Other requests in Sweet Grass County