SOLAR + STORAGE Β· PJM

Solar + storage project AD2-028, Franklin County

Solar + storage project AD2-028, Franklin County is a 150 MW solar + storage request withdrawn in the PJM interconnection queue, in Franklin County, Pennsylvania, connecting to APS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2017 (completed)
  2. Withdrawn / abandonedAug 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AD2-028
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
McConnellsburg-Texas Eastern
Location
Franklin County, Pennsylvania
Technology
Solar: 150 MW Β· Battery
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study
Queue status
Withdrawn
Entered queue
12 December 2017
Proposed online date
June 2019
Withdrawn
August 2018

Location

Marker shows the centre of Franklin County; the queue data does not give exact sites.