United States › Grid › Interconnection queues › Pennsylvania

SOLAR · PJM

Great Cove Solar II

Great Cove Solar II is a 150 MW solar request built and operating in the PJM interconnection queue, in Franklin County, Pennsylvania, connecting to APS.

Queue statusOperating
  1. PlanningQueued Sep 2018 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJun 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AE1-101
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
McConnellsburg-Texas Eastern 138 kV
Location
Franklin County, Pennsylvania
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
2 September 2018
Proposed online date
March 2024
Came online
June 2024

Location

Marker shows the centre of Franklin County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Franklin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem