United States βΊ Grid βΊ Interconnection queues βΊ Florida
SOLAR Β· SOUTHEASTSolar project IC-710, Bay County
Solar project IC-710, Bay County is a 65.0 MW solar request withdrawn in the Southeast interconnection queue, in Bay County, Florida, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2018 (completed)
- Withdrawn / abandonedOct 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IC-710
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Marianna - Bay County 115 kV Line
- Location
- Bay County, Florida
- Technology
- Solar: 65.0 MW
- Total requested
- 65.0 MW
- Service type
- NRIS and ERIS
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 31 May 2018
- Withdrawn
- October 2018
Location
Marker shows the centre of Bay County; the queue data does not give exact sites.
Other requests in Bay County
- Battery storage project 620, Bay CountyBattery storage Β· 400 MW Β· in study
- Solar project 281, Bay CountySolar Β· 74.9 MW Β· built
- Solar project 282, Bay CountySolar Β· 74.9 MW Β· built
- Solar project 328B, Bay CountySolar Β· 50.0 MW Β· built
- Solar project 419A, Bay CountySolar Β· 24.5 MW Β· built
- Gas project IC-758, Bay CountyGas Β· 741 MW Β· withdrawn
- Battery storage project 621, Bay CountyBattery storage Β· 200 MW Β· withdrawn
- Solar project IC-657, Bay CountySolar Β· 50.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem