United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

ONSHORE WIND Β· SPP

Onshore wind project GEN-2008-088, Oldham County

Onshore wind project GEN-2008-088, Oldham County is a 50.6 MW onshore wind request withdrawn in the SPP interconnection queue, in Oldham County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2008 (completed)
  2. Withdrawn / abandonedMay 2015 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2008-088
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Vega 69kV
Location
Oldham County, Texas
Technology
Wind: 50.6 MW
Total requested
50.6 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
12 August 2008
Proposed online date
December 2011
Withdrawn
May 2015

Location

Marker shows the centre of Oldham County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Oldham County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem