Solar 373

Solar 373 is a 408 MW solar + storage request withdrawn in the CAISO interconnection queue, connecting to GLW.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2023 (completed)
  2. Withdrawn / abandonedDec 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
54676
Grid region
CAISO (California)
Utility / transmission owner
GLW
Connection point (POI)
VALLEY SWITCH 230 kV
Location
California
Technology
Solar: 407 MW Β· Battery: 1.0 MW
Total requested
408 MW
Service type
Energy only (ERIS)
Study phase
Caiso Cluster 15 Unvalidated
Queue status
Withdrawn
Entered queue
17 April 2023
Proposed online date
December 2028
Withdrawn
December 2024

Location

Marker shows the centre of County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in County