Solar project AH1-518, Lawrence County

Solar project AH1-518, Lawrence County is a 19.0 MW solar request withdrawn in the PJM interconnection queue, in Lawrence County, Pennsylvania, connecting to ATSI.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2021 (completed)
  2. Withdrawn / abandonedDec 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-518
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ATSI
Connection point (POI)
Pulaski Sub-New Wilmington 69kV
Location
Lawrence County, Pennsylvania
Technology
Solar: 19.0 MW
Total requested
19.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
10 September 2021
Proposed online date
June 2023
Withdrawn
December 2024

Location

Marker shows the centre of Lawrence County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in Lawrence County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem