United States β€Ί Grid β€Ί Interconnection queues β€Ί California

SOLAR Β· CAISO

Rose Solar Project

Rose Solar Project is a 20.0 MW solar request withdrawn in the CAISO interconnection queue, in Fresno County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2010 (completed)
  2. Withdrawn / abandonedJul 2013 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
653E
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Helm Sub 70 kV Bus
Location
Fresno County, California
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
30 September 2010
Proposed online date
February 2014
Withdrawn
July 2013

Location

Marker shows the centre of Fresno County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Fresno County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem