SOLAR + STORAGE Β· WEST

Solar + storage project Company IT, White Pine County

Solar + storage project Company IT, White Pine County is a 120 MW solar + storage request withdrawn in the West interconnection queue, in White Pine County, Nevada, connecting to NV Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2019 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Company IT
Grid region
West (non-ISO utilities)
Utility / transmission owner
NV Energy
Location
White Pine County, Nevada
Technology
Solar: 120 MW Β· Battery
Total requested
120 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
21 September 2019
Proposed online date
September 2022

Location

Marker shows the centre of White Pine County; the queue data does not give exact sites.

Power plants in Nevada Β· Transmission lines in Nevada

Other requests in White Pine County