BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 60.0 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Hartford County, Connecticut.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2022 (completed)
  2. Withdrawn / abandonedAug 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1251
Grid region
ISO-NE (New England)
Connection point (POI)
To interconnect at the POI of Gravel Pit Solar QP 1030, via a Shared Facility, QP 1030 is described as a line cut and three-breaker ring bus of the 115 kV Connecticut Light & Power Company line betwee
Location
Hartford County, Connecticut
Technology
Battery: 60.0 MW
Total requested
60.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
11 April 2022
Proposed online date
December 2024
Withdrawn
August 2022

Location

No county location in the queue data.