BATTERY STORAGE Β· WEST

Battery storage project G0644, Klickitat County

Battery storage project G0644, Klickitat County is a 100 MW battery storage request withdrawn in the West interconnection queue, in Klickitat County, Washington.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2020 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G0644
Grid region
West (non-ISO utilities)
Connection point (POI)
McNary - John Day 500 kV line.
Location
Klickitat County, Washington
Technology
Battery: 100 MW
Total requested
100 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
23 March 2020
Proposed online date
December 2023

Location

Marker shows the centre of Klickitat County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in Klickitat County