United States › Grid › Interconnection queues › Texas
GAS · ERCOTRio Nogales Agp Upgrade CT3
Rio Nogales Agp Upgrade CT3 is a 19.0 MW gas request built and operating in the ERCOT interconnection queue, in Guadalupe County, Texas.
Request details
- Queue ID
- 20INR0272
- Grid region
- ERCOT (Texas)
- Developer
- CPS Energy
- Connection point (POI)
- Existing gen 345kV Rio Nogales Power Project (# 5362)
- Location
- Guadalupe County, Texas
- Technology
- Gas: 19.0 MW
- Total requested
- 19.0 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 9 May 2019
- Proposed online date
- June 2020
- Came online
- June 2020
Location
Marker shows the centre of Guadalupe County; the queue data does not give exact sites.
Other requests in Guadalupe County
- Rockridge SolarSolar · 211 MW · agreement signed
- Nockenut Springs Solar 2Solar · 203 MW · agreement signed
- Nockenut Springs Solar 1Solar · 203 MW · agreement signed
- Rio Nogales CT1 Rotor ReplacementGas · 3.1 MW · agreement signed
- CPS Rio Nogales CT301 Rotor ReplacementGas · 3.1 MW · agreement signed
- CPS Rio Nogales CT201 Rotor ReplacementGas · 3.1 MW · agreement signed
- Calpine Guadalupe PeakersGas · 450 MW · in study
- Guadalupe Battery Storage ProjectBattery storage · 211 MW · in study
- Ruedrich BESSBattery storage · 201 MW · in study
- Aster SolarSolar · 161 MW · in study
- Roble BESSBattery storage · 154 MW · in study
- Utica SolarSolar · 205 MW · suspended
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem