United States β€Ί Grid β€Ί Interconnection queues β€Ί New York

GAS Β· NYISO

Luyster Creek Energy

Luyster Creek Energy is a 444 MW gas request withdrawn in the NYISO interconnection queue, in Queens County, New York, connecting to CONED.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2011 (completed)
  2. Withdrawn / abandonedFeb 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
361
Grid region
NYISO (New York)
Utility / transmission owner
CONED
Developer
US PowerGen Co.
Connection point (POI)
Astoria West Substation 138kV
Location
Queens County, New York
Technology
Gas: 444 MW Β· Oil
Total requested
444 MW
Queue status
Withdrawn
Entered queue
15 February 2011
Withdrawn
February 2020

Location

Marker shows the centre of Queens County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Queens County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem