United States › Grid › Interconnection queues › Maryland
OTHER · PJMSun Paper
Sun Paper is a 4.0 MW other request built and operating in the PJM interconnection queue, in Baltimore City County, Maryland, connecting to BGE.
Request details
- Queue ID
- S30
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- BGE
- Connection point (POI)
- Gould
- Location
- Baltimore City County, Maryland
- Technology
- Diesel: 4.0 MW
- Total requested
- 4.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
- Queue status
- Operational
- Entered queue
- 30 April 2007
- Proposed online date
- August 2008
- Came online
- December 2007
Location
Marker shows the centre of Baltimore City County; the queue data does not give exact sites.
Other requests in Baltimore City County
- Gould StreetGas · 101 MW · built
- Hawkins PointGas · 10.0 MW · built
- Fairfield Renewable Energy FacilityOther · 132 MW · withdrawn
- Fairfield Renewable Energy FacilityOther · 25.0 MW · withdrawn
- Gas project B22, Baltimore City CountyGas · 9.9 MW · withdrawn
- Gas project AE1-151, Baltimore City CountyGas · 9.0 MW · withdrawn
- Battery storage project AB1-020, Baltimore City CountyBattery storage · 0.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem