United States βΊ Grid βΊ Interconnection queues βΊ Maryland
BATTERY STORAGE Β· PJMBattery storage project AB1-020, Baltimore City County
Battery storage project AB1-020, Baltimore City County is a 0.0 MW battery storage request withdrawn in the PJM interconnection queue, in Baltimore City County, Maryland, connecting to BGE.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2015 (completed)
- Withdrawn / abandonedSep 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AB1-020
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- BGE
- Connection point (POI)
- Cold Spring 240v
- Location
- Baltimore City County, Maryland
- Technology
- Battery: 0.0 MW
- Total requested
- 0.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- Interim/Interconnection Service Agreement: Wholesale Market Participation Agreement
- Queue status
- Withdrawn
- Entered queue
- 29 June 2015
- Proposed online date
- December 2015
- Withdrawn
- September 2019
Location
Marker shows the centre of Baltimore City County; the queue data does not give exact sites.
Other requests in Baltimore City County
- Gould StreetGas Β· 101 MW Β· built
- Hawkins PointGas Β· 10.0 MW Β· built
- Sun PaperOther Β· 4.0 MW Β· built
- Fairfield Renewable Energy FacilityOther Β· 132 MW Β· withdrawn
- Fairfield Renewable Energy FacilityOther Β· 25.0 MW Β· withdrawn
- Gas project B22, Baltimore City CountyGas Β· 9.9 MW Β· withdrawn
- Gas project AE1-151, Baltimore City CountyGas Β· 9.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem