Hobnail Solar

Hobnail Solar is a 70.0 MW solar request built and operating in the Southeast interconnection queue, in Burke County, Georgia, connecting to Southern Company.

Queue statusOperating
  1. PlanningQueued Aug 2019 (completed)
  2. ConsentedMar 2021 (completed)
  3. Construction (completed)
  4. OperatingMay 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
IC-803
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Location
Burke County, Georgia
Technology
Solar: 70.0 MW
Total requested
70.0 MW
Study phase
Operational
Queue status
Operational
Entered queue
27 August 2019
Agreement signed
29 March 2021
Proposed online date
July 2022
Came online
May 2024

Location

Marker shows the centre of Burke County; the queue data does not give exact sites.

Power plants in Georgia · Transmission lines in Georgia

Other requests in Burke County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem