United States › Grid › Interconnection queues › Georgia
SOLAR · SOUTHEASTHobnail Solar
Hobnail Solar is a 70.0 MW solar request built and operating in the Southeast interconnection queue, in Burke County, Georgia, connecting to Southern Company.
Request details
- Queue ID
- IC-803
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Location
- Burke County, Georgia
- Technology
- Solar: 70.0 MW
- Total requested
- 70.0 MW
- Study phase
- Operational
- Queue status
- Operational
- Entered queue
- 27 August 2019
- Agreement signed
- 29 March 2021
- Proposed online date
- July 2022
- Came online
- May 2024
Location
Marker shows the centre of Burke County; the queue data does not give exact sites.
Other requests in Burke County
- Solar project IC-759, Burke CountySolar · 40.0 MW · agreement signed
- Solar project 25-IC-1340, Burke CountySolar · 175 MW · in study
- TOCE GA 1 SolarSolar · 125 MW · in study
- Nuclear project 25-IC-1300, Burke CountyNuclear · 50.0 MW · in study
- Nuclear project 25-IC-1298, Burke CountyNuclear · 50.0 MW · in study
- Nuclear project 25-IC-1303, Burke CountyNuclear · 20.0 MW · in study
- Nuclear project 25-IC-1304, Burke CountyNuclear · 16.0 MW · in study
- Nuclear project 25-IC-1297, Burke CountyNuclear · 15.0 MW · in study
- Nuclear project 25-IC-1299, Burke CountyNuclear · 15.0 MW · in study
- Solar project IC-1005, Burke CountySolar · 100 MW · suspended
- Vogtle Unit 3Nuclear · 1,158 MW · built
- Vogtle Unit 4Nuclear · 1,158 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem