πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New York

HYDRO Β· NYISO

Seth Green

Seth Green is a 2.8 MW hydro request withdrawn in the NYISO interconnection queue, in Monroe County, New York, connecting to RG&E.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2007 (completed)
  2. Withdrawn / abandonedMar 2014 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
264
Grid region
NYISO (New York)
Utility / transmission owner
RG&E
Developer
RG&E
Connection point (POI)
11kV
Location
Monroe County, New York
Technology
Hydro: 2.8 MW
Total requested
2.8 MW
Queue status
Withdrawn
Entered queue
23 October 2007
Withdrawn
March 2014

Location

Marker shows the centre of Monroe County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Monroe County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem