GAS · CAISOFresno Cogen Ice Unit
Fresno Cogen Ice Unit is a 0.6 MW gas request built and operating in the CAISO interconnection queue, in Fresno County, California, connecting to PGAE.
Request details
- Queue ID
- 51
- Grid region
- CAISO (California)
- Utility / transmission owner
- PGAE
- Connection point (POI)
- Kerman-Helm 70kV line
- Location
- Fresno County, California
- Technology
- Gas: 0.6 MW
- Total requested
- 0.6 MW
- Study phase
- Executed
- Queue status
- Operational
- Entered queue
- 21 December 2004
- Proposed online date
- April 2005
- Came online
- May 2006
Location
Marker shows the centre of Fresno County; the queue data does not give exact sites.
Power plants in California · Transmission lines in California
Other requests in Fresno County
- DardenSolar + storage · 2,365 MW · agreement signed
- ScarletSolar + storage · 800 MW · agreement signed
- Cornucopia HybridSolar + storage · 605 MW · agreement signed
- Lock StorageBattery storage · 508 MW · agreement signed
- ElysianSolar + storage · 412 MW · agreement signed
- ClarksonSolar + storage · 408 MW · agreement signed
- SonrisaSolar + storage · 384 MW · agreement signed
- Luna Valley SolarSolar + storage · 373 MW · agreement signed
- Key Storage 1Battery storage · 309 MW · agreement signed
- Ciervo Mountain HybridSolar + storage · 255 MW · agreement signed
- Midway PeakingGas · 240 MW · agreement signed
- Heartland 2Solar + storage · 228 MW · agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem