Solar project Q35, Clark County

Solar project Q35, Clark County is a 250 MW solar request built and operating in the West interconnection queue, in Clark County, Nevada, connecting to Los Angeles Department of Water and Power.

Queue statusOperating
  1. PlanningQueued Oct 2012 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Q35
Grid region
West (non-ISO utilities)
Utility / transmission owner
Los Angeles Department of Water and Power
Connection point (POI)
Crystal-Moapa 500kV Line
Location
Clark County, Nevada
Technology
Solar: 250 MW
Total requested
250 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
19 October 2012
Proposed online date
February 2014
Came online
December 2016

Location

Marker shows the centre of Clark County; the queue data does not give exact sites.