Plant Road BESS

Plant Road BESS is a 206 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Ector County, Texas.

Queue statusIn planning
  1. PlanningQueued Oct 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
27INR0343
Grid region
ERCOT (Texas)
Developer
Horizon Energy Storage Greenfield Project Holdings LLC
Connection point (POI)
1027 ODEHV 138kV
Location
Ector County, Texas
Technology
Battery: 206 MW
Total requested
206 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
10 October 2024
Proposed online date
March 2028

Location

Marker shows the centre of Ector County; the queue data does not give exact sites.