πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί California

SOLAR Β· CAISO

Re Alpine

Re Alpine is a 20.0 MW solar request withdrawn in the CAISO interconnection queue, in Fresno County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2011 (completed)
  2. Withdrawn / abandonedJun 2011 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
745
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Coalinga - Gates #1 70 KV
Location
Fresno County, California
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
31 March 2011
Proposed online date
December 2013
Withdrawn
June 2011

Location

Marker shows the centre of Fresno County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Fresno County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem