πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· SPP

Solar project GEN-2015-037, Hale County

Solar project GEN-2015-037, Hale County is a 253 MW solar request withdrawn in the SPP interconnection queue, in Hale County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2015 (completed)
  2. Withdrawn / abandonedApr 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2015-037
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
TUCO 345kV substation
Location
Hale County, Texas
Technology
Solar: 253 MW
Total requested
253 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
23 September 2015
Proposed online date
June 2018
Withdrawn
April 2016

Location

Marker shows the centre of Hale County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Hale County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem