United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· SPP

Solar project GEN-2016-015, Andrews County

Solar project GEN-2016-015, Andrews County is a 100 MW solar request withdrawn in the SPP interconnection queue, in Andrews County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2016 (completed)
  2. Withdrawn / abandonedAug 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2016-015
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Andrews County 230kV
Location
Andrews County, Texas
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
29 March 2016
Proposed online date
October 2018
Withdrawn
August 2019

Location

Marker shows the centre of Andrews County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Andrews County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem