United States › Grid › Interconnection queues › California

SOLAR · CAISO

Calrenew-1(A)

Calrenew-1(A) is a 5.0 MW solar request built and operating in the CAISO interconnection queue, in Fresno County, California, connecting to PGAE.

Queue statusOperating
  1. PlanningQueued Oct 2007 (completed)
  2. ConsentedOct 2008 (completed)
  3. Construction (completed)
  4. OperatingApr 2010 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
261A
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Mendota-San Joaquin-Helm 70kV line
Location
Fresno County, California
Technology
Solar: 5.0 MW
Total requested
5.0 MW
Study phase
Executed
Queue status
Operational
Entered queue
9 October 2007
Agreement signed
14 October 2008
Proposed online date
April 2009
Came online
April 2010

Location

Marker shows the centre of Fresno County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Fresno County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem