πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Utah

GEOTHERMAL Β· WEST

Geothermal project 326-F, Beaver County

Geothermal project 326-F, Beaver County is a 21.2 MW geothermal request withdrawn in the West interconnection queue, in Beaver County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2010 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
326-F
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Milford substation
Location
Beaver County, Utah
Technology
Geothermal: 21.2 MW
Total requested
21.2 MW
Service type
Network resource (NRIS)
Study phase
REMOVED-LACK OF PROGRESS
Queue status
Withdrawn
Entered queue
16 March 2010
Proposed online date
July 2014

Location

Marker shows the centre of Beaver County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah

Other requests in Beaver County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem