United States › Grid › Interconnection queues › California
SOLAR + STORAGE · WESTSolar + storage project 2023-G2, Fresno County
Solar + storage project 2023-G2, Fresno County is a 800 MW solar + storage request in interconnection study in the West interconnection queue, in Fresno County, California, connecting to WAPA Sierra Nevada.
- PlanningQueued Mar 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 2023-G2
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- WAPA Sierra Nevada
- Connection point (POI)
- New Point 500 kV Substation
- Location
- Fresno County, California
- Technology
- Solar: 800 MW · Battery
- Total requested
- 800 MW
- Service type
- NRIS and ERIS
- Study phase
- Includes a New Point to Tracy 500 kV line as part of Project.
- Queue status
- Active
- Entered queue
- 1 March 2023
- Proposed online date
- June 2028
Location
Marker shows the centre of Fresno County; the queue data does not give exact sites.
Power plants in California · Transmission lines in California
Other requests in Fresno County
- DardenSolar + storage · 2,365 MW · agreement signed
- ScarletSolar + storage · 800 MW · agreement signed
- Cornucopia HybridSolar + storage · 605 MW · agreement signed
- Lock StorageBattery storage · 508 MW · agreement signed
- ElysianSolar + storage · 412 MW · agreement signed
- ClarksonSolar + storage · 408 MW · agreement signed
- SonrisaSolar + storage · 384 MW · agreement signed
- Luna Valley SolarSolar + storage · 373 MW · agreement signed
- Key Storage 1Battery storage · 309 MW · agreement signed
- Ciervo Mountain HybridSolar + storage · 255 MW · agreement signed
- Midway PeakingGas · 240 MW · agreement signed
- Heartland 2Solar + storage · 228 MW · agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem