United States β€Ί Grid β€Ί Interconnection queues β€Ί New Jersey

GAS Β· PJM

Gas project AC1-196, Gloucester County

Gas project AC1-196, Gloucester County is a 0.2 MW gas request withdrawn in the PJM interconnection queue, in Gloucester County, New Jersey, connecting to AEC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2016 (completed)
  2. Withdrawn / abandonedNov 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AC1-196
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEC
Connection point (POI)
Mantua 12kV
Location
Gloucester County, New Jersey
Technology
Gas: 0.2 MW
Total requested
0.2 MW
Service type
Energy only (ERIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
31 October 2016
Proposed online date
June 2017
Withdrawn
November 2016

Location

Marker shows the centre of Gloucester County; the queue data does not give exact sites.

Power plants in New Jersey Β· Transmission lines in New Jersey

Other requests in Gloucester County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem