SOLAR · SOUTHEASTSolar project 321, Sumter County
Solar project 321, Sumter County is a 74.9 MW solar request built and operating in the Southeast interconnection queue, in Sumter County, Florida, connecting to Duke Energy Florida.
Request details
- Queue ID
- 321
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Duke Energy Florida
- Developer
- Duke Energy Florida, LLC
- Connection point (POI)
- Crescent Substation
- Location
- Sumter County, Florida
- Technology
- Solar: 74.9 MW
- Total requested
- 74.9 MW
- Service type
- NRIS and ERIS
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 16 December 2022
- Proposed online date
- December 2025
- Came online
- December 2025
Location
Marker shows the centre of Sumter County; the queue data does not give exact sites.
Other requests in Sumter County
- Solar project 322, Sumter CountySolar · 74.9 MW · under construction
- Solar project FC100004, Sumter CountySolar · 74.9 MW · in study
- Nuclear project 8, Sumter CountyNuclear · 1,150 MW · withdrawn
- Other project 144, Sumter CountyOther · 560 MW · withdrawn
- Solar project 271, Sumter CountySolar · 74.5 MW · withdrawn
- Solar project 266, Sumter CountySolar · 74.5 MW · withdrawn
- Solar project 233, Sumter CountySolar · 74.5 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem