ONSHORE WIND Β· WEST

Onshore wind project G0261, Klickitat County

Onshore wind project G0261, Klickitat County is a 1,200 MW onshore wind request withdrawn in the West interconnection queue, in Klickitat County, Washington.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2007 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G0261
Grid region
West (non-ISO utilities)
Connection point (POI)
Ashe-Marion 500 kV
Location
Klickitat County, Washington
Technology
Wind: 1,200 MW
Total requested
1,200 MW
Service type
Energy only (ERIS)
Queue status
Withdrawn
Entered queue
22 February 2007
Proposed online date
September 2010

Location

Marker shows the centre of Klickitat County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in Klickitat County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem