πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New York

GAS Β· NYISO

Berrians GT

Berrians GT is a 200 MW gas request withdrawn in the NYISO interconnection queue, in Queens County, New York, connecting to CONED.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2005 (completed)
  2. Withdrawn / abandonedJul 2015 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
201
Grid region
NYISO (New York)
Utility / transmission owner
CONED
Developer
NRG Energy
Connection point (POI)
Astoria West Substation 138kV
Location
Queens County, New York
Technology
Gas: 200 MW
Total requested
200 MW
Queue status
Withdrawn
Entered queue
17 August 2005
Withdrawn
July 2015

Location

Marker shows the centre of Queens County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Queens County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem