BATTERY STORAGE · CAISO

Firebaugh Panoche BESS (Fka Panoche Energy Reliability Center)

Firebaugh Panoche BESS (Fka Panoche Energy Reliability Center) is a 50.0 MW battery storage request withdrawn in the CAISO interconnection queue, in Fresno County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2015 (completed)
  2. Withdrawn / abandonedMar 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1123
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Panoche-Schindler #2 115 kV Line via the Cheney #1 Tap 115 kV Line
Location
Fresno County, California
Technology
Battery: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
30 April 2015
Proposed online date
May 2018
Withdrawn
March 2016

Location

Marker shows the centre of Fresno County; the queue data does not give exact sites.