United States › Grid › Interconnection queues › New York

BATTERY STORAGE · NYISO

Astoria Storage on Demand

Astoria Storage on Demand is a 15.0 MW battery storage request withdrawn in the NYISO interconnection queue, in Queens County, New York, connecting to ConEd.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2018 (completed)
  2. Withdrawn / abandonedMar 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
692
Grid region
NYISO (New York)
Utility / transmission owner
ConEd
Developer
Consolidated Edison Company of NY, Inc.
Connection point (POI)
North Queens Substation
Location
Queens County, New York
Technology
Battery: 15.0 MW
Total requested
15.0 MW
Queue status
Withdrawn
Entered queue
7 February 2018
Withdrawn
March 2018

Location

Marker shows the centre of Queens County; the queue data does not give exact sites.