United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTRockhound Solar
Rockhound Solar is a 250 MW solar request withdrawn in the ERCOT interconnection queue, in Ector County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2019 (completed)
- Withdrawn / abandonedMay 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 20INR0251
- Grid region
- ERCOT (Texas)
- Developer
- Rockhound Solar 1, LLC
- Connection point (POI)
- tap 138kV 1027 Odessa - 1107 Monahans
- Location
- Ector County, Texas
- Technology
- Solar: 250 MW
- Total requested
- 250 MW
- Study phase
- FIS & SS Incomplete
- Queue status
- Withdrawn
- Entered queue
- 27 February 2019
- Proposed online date
- June 2020
- Withdrawn
- May 2019
Location
Marker shows the centre of Ector County; the queue data does not give exact sites.
Other requests in Ector County
- Greyhound SolarSolar Β· 336 MW Β· agreement signed
- Sisters SolarSolar + storage Β· 302 MW Β· agreement signed
- Greyhound Solar - Phase ESolar Β· 151 MW Β· agreement signed
- Greyhound Solar - Phase FSolar Β· 102 MW Β· agreement signed
- Apple BESSBattery storage Β· 9.9 MW Β· agreement signed
- Gypsum Plains SolarSolar + storage Β· 503 MW Β· in study
- Velociraptor BESS IISolar + storage Β· 261 MW Β· in study
- Velociraptor BESS ISolar + storage Β· 261 MW Β· in study
- Van Zandt Energy StorageBattery storage Β· 257 MW Β· in study
- Velociraptor Solar IISolar + storage Β· 252 MW Β· in study
- Velociraptor Solar ISolar + storage Β· 252 MW Β· in study
- Gypsum Plains StorageSolar + storage Β· 211 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem