Solar project 310, Iron County

Solar project 310, Iron County is a 20.0 MW solar request withdrawn in the West interconnection queue, in Iron County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2009 (completed)
  2. Withdrawn / abandonedMay 2018 (project stopped here)
  3. ConsentedDec 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
310
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Parowan substation circuit
Location
Iron County, Utah
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
IA signed 12/20/11, IA Terminated 5/2/18
Queue status
Withdrawn
Entered queue
21 December 2009
Agreement signed
20 December 2011
Proposed online date
October 2010
Withdrawn
May 2018

Location

Marker shows the centre of Iron County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah