πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Utah

SOLAR Β· WEST

Solar project 367, Iron County

Solar project 367, Iron County is a 172 MW solar request withdrawn in the West interconnection queue, in Iron County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2010 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
367
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Sigurd-Red Butte line
Location
Iron County, Utah
Technology
Solar: 172 MW
Total requested
172 MW
Service type
Network resource (NRIS)
Study phase
WITHDRAWN BY CUSTOMER
Queue status
Withdrawn
Entered queue
27 December 2010
Proposed online date
January 2014

Location

Marker shows the centre of Iron County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah

Other requests in Iron County