BATTERY STORAGE Β· PJM

Battery storage project AH1-480, Van Wert County

Battery storage project AH1-480, Van Wert County is a 57.0 MW battery storage request withdrawn in the PJM interconnection queue, in Van Wert County, Ohio, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2021 (completed)
  2. Withdrawn / abandonedDec 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-480
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Haviland β€šΓ„Γ¬ Cavett Switch 69 kV
Location
Van Wert County, Ohio
Technology
Battery: 57.0 MW
Total requested
57.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
10 September 2021
Proposed online date
September 2023
Withdrawn
December 2024

Location

Marker shows the centre of Van Wert County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Van Wert County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem