Prospero Solar II

Prospero Solar II is a 250 MW solar request built and operating in the ERCOT interconnection queue, in Andrews County, Texas.

Queue statusOperating
  1. PlanningQueued Nov 2018 (completed)
  2. ConsentedJan 2020 (completed)
  3. Construction (completed)
  4. OperatingSep 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
21INR0229
Grid region
ERCOT (Texas)
Developer
Prospero Solar II, LLC
Connection point (POI)
11270 Dog House Switch 345 kv
Location
Andrews County, Texas
Technology
Solar: 250 MW
Total requested
250 MW
Study phase
IA
Queue status
Operational
Entered queue
28 November 2018
Agreement signed
17 January 2020
Proposed online date
September 2021
Came online
September 2021

Location

Marker shows the centre of Andrews County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Andrews County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem