Felix North Solar Placeholder

Felix North Solar Placeholder is a 201 MW solar request withdrawn in the ERCOT interconnection queue, in Wilbarger County, Texas.

Queue statusWithdrawn / abandoned
  1. Planning (completed)
  2. Withdrawn / abandonedNov 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
27INR0599
Grid region
ERCOT (Texas)
Developer
Felix 1, LLC
Connection point (POI)
345 kV Riley Substation (#6101)
Location
Wilbarger County, Texas
Technology
Solar: 201 MW
Total requested
201 MW
Study phase
FIS & SS Incomplete
Queue status
Withdrawn
Proposed online date
July 2027
Withdrawn
November 2025

Location

Marker shows the centre of Wilbarger County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Wilbarger County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem