United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTFelix North Solar Placeholder
Felix North Solar Placeholder is a 201 MW solar request withdrawn in the ERCOT interconnection queue, in Wilbarger County, Texas.
Queue statusWithdrawn / abandoned
- Planning (completed)
- Withdrawn / abandonedNov 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 27INR0599
- Grid region
- ERCOT (Texas)
- Developer
- Felix 1, LLC
- Connection point (POI)
- 345 kV Riley Substation (#6101)
- Location
- Wilbarger County, Texas
- Technology
- Solar: 201 MW
- Total requested
- 201 MW
- Study phase
- FIS & SS Incomplete
- Queue status
- Withdrawn
- Proposed online date
- July 2027
- Withdrawn
- November 2025
Location
Marker shows the centre of Wilbarger County; the queue data does not give exact sites.
Other requests in Wilbarger County
- Felix North SolarSolar + storage · 201 MW · agreement signed
- Felix West SolarSolar + storage · 201 MW · agreement signed
- Felix East SolarSolar + storage · 201 MW · agreement signed
- Dundee West WindOnshore wind · 146 MW · agreement signed
- Blue Summit Energy StorageWind + storage · 100 MW · agreement signed
- Limitless Energy Hub IGas · 1,238 MW · in study
- Limitless Energy Hub IIGas · 1,238 MW · in study
- TexpoGas · 680 MW · in study
- Reunion SolarSolar + storage · 601 MW · in study
- Big Field SolarSolar · 506 MW · in study
- Poco Trail SolarSolar · 439 MW · in study
- Wander Waters BESSBattery storage · 304 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem