πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Utah

GEOTHERMAL Β· WEST

Geothermal project 321, Beaver County

Geothermal project 321, Beaver County is a 50.0 MW geothermal request withdrawn in the West interconnection queue, in Beaver County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2010 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
321
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
substation, located near the Mother Earth tap point
Location
Beaver County, Utah
Technology
Geothermal: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
WITHDRAWN BY CUSTOMER
Queue status
Withdrawn
Entered queue
19 February 2010
Proposed online date
July 2016

Location

Marker shows the centre of Beaver County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah

Other requests in Beaver County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem