United States βΊ Grid βΊ Interconnection queues βΊ Minnesota
ONSHORE WIND Β· MISOOnshore wind project G040, Nobles County
Onshore wind project G040, Nobles County is a 202 MW onshore wind request withdrawn in the MISO interconnection queue, in Nobles County, Minnesota.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2000 (completed)
- Withdrawn / abandonedDec 2003 (project stopped here)
- ConsentedDec 2003 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G040
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Unknown
- Location
- Nobles County, Minnesota
- Technology
- Wind: 202 MW
- Total requested
- 202 MW
- Queue status
- Withdrawn
- Entered queue
- 30 May 2000
- Agreement signed
- 17 December 2003
- Proposed online date
- May 2002
- Withdrawn
- December 2003
Location
Marker shows the centre of Nobles County; the queue data does not give exact sites.
Power plants in Minnesota Β· Transmission lines in Minnesota
Other requests in Nobles County
- Nobles BESSBattery storage Β· 314 MW Β· in study
- Solar project J1581, Nobles CountySolar Β· 200 MW Β· in study
- SurplusBattery storage Β· 200 MW Β· in study
- Onshore wind project J512, Nobles CountyOnshore wind Β· 250 MW Β· built
- Onshore wind project G162, Nobles CountyOnshore wind Β· 200 MW Β· built
- Onshore wind project G287, Nobles CountyOnshore wind Β· 200 MW Β· built
- Onshore wind project G602, Nobles CountyOnshore wind Β· 32.0 MW Β· built
- Onshore wind project G374, Nobles CountyOnshore wind Β· 6.0 MW Β· built
- Other project G140, Nobles CountyOther Β· 2.0 MW Β· built
- Other project G270, Nobles CountyOther Β· 2.0 MW Β· built
- Other project G142, Nobles CountyOther Β· 2.0 MW Β· built
- Onshore wind project G385, Nobles CountyOnshore wind Β· 2.0 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem