Onshore wind project GEN-2017-078, Roosevelt County

Onshore wind project GEN-2017-078, Roosevelt County is a 220 MW onshore wind request withdrawn in the SPP interconnection queue, in Roosevelt County, New Mexico, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2017 (completed)
  2. Withdrawn / abandonedMay 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2017-078
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Eddy County-Tolk (Crossroads) 345kV
Location
Roosevelt County, New Mexico
Technology
Wind: 220 MW
Total requested
220 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
30 May 2017
Proposed online date
December 2020
Withdrawn
May 2021

Location

Marker shows the centre of Roosevelt County; the queue data does not give exact sites.