Lapetus Solar

Lapetus Solar is a 50.0 MW solar request withdrawn in the ERCOT interconnection queue, in Andrews County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2018 (completed)
  2. Withdrawn / abandonedJan 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
19INR0149
Grid region
ERCOT (Texas)
Developer
7x Energy
Connection point (POI)
1284 Shafter Lake 138kV
Location
Andrews County, Texas
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Study phase
FIS Complete
Queue status
Withdrawn
Entered queue
21 February 2018
Proposed online date
November 2019
Withdrawn
January 2019

Location

Marker shows the centre of Andrews County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Andrews County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem